By David Starr on Monday, 20 May 2024
Category: Products

Case Study: Open-Cell Spray Foam Removal

Project Overview

Our team was contracted to remove internal spray foam insulation from a 110m² roof area. The task involved carefully removing the spray foam insulation applied directly to the interior roof structure, ensuring that all rafters, hips, and ridge boards were left clean and free from any remaining foam. This case study outlines the scope of work, challenges faced, and the results of the project.

Scope of Work

The key tasks for this project included:

  1. Preparation and Site Setup:
    • Ensured the area was secure and protected from debris during the removal process.
    • Organised the site with appropriate safety measures, including dust sheets and protective equipment to safeguard both workers and the interior of the property.
  2. Removal of Internal Spray Foam Insulation:
    • Carefully removed the spray foam insulation from the internal roof structure, paying close attention to avoid damaging the underlying rafters, hips, and ridge boards.
    • Utilised specialised tools for scraping and peeling away the foam, ensuring that all surfaces were thoroughly cleaned of any residual insulation.
  3. Inspection and Cleaning of Roof Structure:
    • Inspected all rafters, hips, and ridge boards for any damage or signs of wear caused by the insulation.
    • Sanded and cleaned the exposed timber to prepare it for any necessary treatments or repairs.
  4. Waste Management and Disposal:
    • All foam and debris were collected and disposed of using licensed waste carriers, adhering to environmental regulations and best practices for waste management.
  5. Site Clean-Up:
    • Completed a thorough clean-up of the work area, ensuring no debris or dust was left behind and the property was returned to its original condition.

Challenges and Solutions

  • Delicate Foam Removal: Removing spray foam from internal roof structures requires precision to avoid damaging the timber. Our team used a combination of manual scraping and careful sanding techniques to protect the structural integrity of the roof.
  • Waste Management: Efficiently managing the removal of large quantities of foam was essential. By using licensed waste carriers and ensuring all waste was properly compacted and disposed of, we maintained a clean and compliant worksite.
  • Outcome

    The project was completed successfully, with all 110m² of internal spray foam insulation removed and the roof structure left clean and ready for any further work required by the client. The job was completed on time and within budget, demonstrating our commitment to high standards of workmanship and customer satisfaction.

    Key Benefits to the Client:

  • Improved Roof Accessibility: By removing the internal spray foam, the roof structure is now fully exposed and accessible for inspections, repairs, or future insulation upgrades.
  • Enhanced Structural Integrity: The careful removal process ensured that no damage occurred to the rafters or other critical elements, preserving the integrity of the roof.
  • Compliance and Cleanliness: The project adhered to all relevant waste management regulations, and the site was left clean and tidy, meeting the client's expectations.
  • Spray Foam Removal ​

    Before 

    After 

    Before 

    After 

    Conclusion

    This internal spray foam removal project highlights our expertise in handling sensitive insulation removal tasks while preserving the underlying roof structure. Our careful approach ensures that properties are left in a clean, safe state, ready for the next phase of maintenance or upgrades.