Open-Cell Spray Foam Removal and Loft Insulation Top-Up
Countrywide Roofing & Insulation removed 50m² of open-cell spray foam and completed a 40m² loft insulation top-up, exposing the roof lining and timbers while adding insulation at loft-floor level.
Project overview
| Detail | Project |
|---|---|
| Open-cell spray foam removal | 50m² |
| Loft insulation top-up | 40m² |
| Roof construction | Pitched roof with timber trusses |
| Existing loft features | Ladder, lighting and a boarded central section |
Removing foam around the roof trusses
The original installation covered the roof lining between the rafters and extended behind the diagonal timber supports. Our team worked through the individual roof bays and around the trusses, removing the open-cell foam to reveal the lining beneath.
The existing ladder, lighting and central boarding provided access into and through the loft. The after photographs show individual rafters and roof bays visible where foam had previously covered the roof underside.
Topping up the loft insulation
Alongside the removal, we topped up 40m² of insulation at loft-floor level. This addressed a separate part of the loft: foam was removed from the roof slopes while additional insulation was installed below. The central boarded section remained part of the existing layout.
The result
The completed work combined 50m² of open-cell spray foam removal with a 40m² insulation top-up. The photographed roof lining and timber surfaces became more accessible for visual inspection, with the before-and-after collage recording the change.
Arrange an inspection and quotation